Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project an 11% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.)
Group of answer choices
from 106.49 to 106.65 days
from 106.97 to 107.13 days
from 106.33 to 106.49 days
from 106.81 to 106.97 days
from 106.65 to 106.81 days
PreviousNext
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started