Question

1 Approved Answer

A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project an 80% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.)

Group of answer choices from 137.42 to 137.54 days from 137.66 to 137.78 days from 137.18 to 137.3 days from 137.54 to 137.66 days from 137.3 to 137.42 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting What the Numbers Mean

Authors: David Marshall, Wayne McManus, Daniel Viele

12th edition

978-1260565492

Students also viewed these General Management questions