Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A project comprises of activities A , B , C , D , E , F . The duration of project is 2 5 7

A project comprises of activities A, B, C, D, E, F. The duration of project is 257 days. The duration for activity D is 72 days and it has the slack of 28 days. Suppose activity D is delayed and no other activity is delayed. As a result of this delay in D, the project duration increased by 23 days.
What is the delay (in number of days) in activity D?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these General Management questions