A project consists of nine jobs (A, B, C, D, E, F, G, H and I) with the following preceding activities and time estimates in days. Job Preceding activity Optimistic time Most likely time Pessimistic time ABCDEFGHI (a) (m) (b) 4 7 4 A, B 7 A, B 3 B 6 D, E 4 C, F 4 D, E 2 G, H 3 63627256 15 13 30 12 18 16 10 28 6509868800 16 (a) Construct the project network for the activities (b) Determine the critical path and the expected duration (c) Determine the probability that the project will be completed in 50 days (d) Calculate the total float on the non-critical activities (15 Marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Lets break down the solution step by step a Construct the project network for the activities To construct the project network also known as a PERT chart you need to represent all jobs their dependenci... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions