A project consists of the following tasks, with task times in weeks. Use the data provided to identify theproject's critical path. Task Preceding Task to
A project consists of the following tasks, with task times in weeks. Use the data provided to identify theproject's critical path. Task Preceding Task to tm tp A 3 15 18 B 10 11 15 C A 4 13 15 D B 6 8 20 E C, D 4 13 19 F E 4 9 20 G F 8 11 18 What is the project's critical path