A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are

A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and three days with a probability of 0.5. What is the expected completion time of the project?

multiple choice

a.) 8 Days

b.) 10 Days

c.) 11 Days

d.) 12 Days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: R. Dan Reid, Nada R. Sanders

4th edition

9780470556702, 470325046, 470556706, 978-0470325049

More Books

Students also viewed these General Management questions

Question

Can generalizations be made on the basis of these estimates?

Answered: 1 week ago