A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are
A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and three days with a probability of 0.5. What is the expected completion time of the project?
multiple choice
a.) 8 Days
b.) 10 Days
c.) 11 Days
d.) 12 Days