A project has 1 0 tasks: A , B , C , D , E , F , G , H , I, and J

A project has 10 tasks: A, B, C, D, E, F, G, H, I, and J, which are detailed and sequenced.
of the work as follows
work
Work that needs to be done
Finished first.
Normal working hours
(week)
Minimum acceleration time
(week)
Cost of acceleration per week
(Baht per week)
A 64500
B 43300
C 86300
D 87300
E 641000
F 21400
G 108900
H 86800
I 97700
J 1071100
So
Critical tasks of each critical path
If the budget for accelerating work is 4,000 baht, which tasks must be accelerated and how many of each?
Weeks: How many weeks are left for the project's completion? How much budget is used to accelerate the workproject has 10 tasks: A, B, C, D, E, F, G, H, I, and J, which are detailed and sequenced.
of the work as follows
work
Work that needs to be done
Finished first.
Normal working hours
(week)
Minimum acceleration time
(week)
Cost of acceleration per week
(Baht per week)
A 64500
B 43300
C 86300
D 87300
E 641000
F 21400
G 108900
H 86800
I 97700
J 1071100
So
Critical tasks of each critical path

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: Donald Waters

5th Edition

273739476, 978-0273739470

More Books

Students also viewed these General Management questions