A project has a budget of $10K. At time X, it's supposed to be finished, but only 80% has been finished in reality. Assume S7K
A project has a budget of $10K. At time X, it's supposed to be finished, but only 80% has been finished in reality. Assume S7K is the actual cost. What are the schedule performance index and cost performance index? Show all work. No excel calculations if applicable
Answers:
0.8 and 1.14
0.8 and 0.7
0.8 and 0.875
1.25 and 1.14