A project has a total budgeted cost 65599 dollars. The project is in its performing phase. At the end of week 14, the progress report

image text in transcribed
A project has a total budgeted cost 65599 dollars. The project is in its performing phase. At the end of week 14, the progress report shows that the project has a cost of performance index of 0.91 and a cost variance of -10517 dollars. The cumulative budgeted cost should be 36759 dollars. What is the estimated project cost at completion if the project continues at the CPI observed at the end of week 14. Use at least 4 decimals and do NOT use any comma in your

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Reporting Exam Kit Kaplan Approved Acca

Authors: Kaplan Publishing

1st Edition

9781787404137

More Books

Students also viewed these Accounting questions

Question

Find the asymptotes of the hyperbola given by 2y2 - x2 = 18.

Answered: 1 week ago

Question

Distinguish between formal and informal reports.

Answered: 1 week ago