Question
1 Approved Answer
A project has an NPV of R.O. 12,632 when a discount rate of 12% is used and the same project has an NPV of R.O.
A project has an NPV of R.O. 12,632 when a discount rate of 12% is used and the same project has an NPV of R.O. -6,935 when a discount rate of 22% is used, the actual internal rate of return of the project is:
Select one:
a.
28.50%
b.
6.50%
c.
18.50%
d.
16.50%
Step by Step Solution