A project has been defined to contain the following activities, along with their time estimates ( in weeks ) for completion: Activity Optimistic time Most

A project has been defined to contain the following activities, along with their time estimates (in weeks) for completion:
Activity
Optimistic time
Most likely time
Pessimistic time
Immediate Predecessor
A
1
4
7
-
B
2
6
7
A
C
3
4
6
D
D
6
12
14
A
E
3
6
12
D
F
6
8
16
B, C
G
1
5
6
E, F
What is the probability that this project will take over (i.e., more than)32 weeks to complete?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker

4th Edition

0134744934, 9780134744933

More Books

Students also viewed these General Management questions

Question

2 28 105

Answered: 1 week ago