A project has been defined to contain the following list of activities, along with their normal time (weeks), crash time (weeks), normal costs ($000), and
A project has been defined to contain the following list of activities, along with their normal time (weeks), crash time (weeks), normal costs ($000), and crash costs ($000). Normal Normal Crash Crash Activity - Predecessors Time (week) Cost (in k) Time - Cost (in k) A --- 5 7 3 13 B A 10 12 7 18 G A 8 5 7 D B 6 4 5 5 E