A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes
A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed. Which project artifact should the risk manager analyze to mitigate the risk of further project overrun? Contingency reserves Risk impact matrix Schedule and resource assumptions Work breakdown structure (WBS)