Question
1 Approved Answer
A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and
A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project?
A B
A C D
Cannot be determined from the information given
A B D