A project has four major activities. Activity A precedes activity B. activity C precedes activity D. 3point estimates for activities are A(11. 22, 33 )
A project has four major activities. Activity A precedes activity B. activity C precedes activity D. 3point estimates for activities are A(11. 22, 33 ) E-{ T. 14, 21 i; C( 2. 4. 6 }, D( 16, 32, 48 )weeks. What probability would you assign to a project duration of more than 36 weeks\"? "'3' a. 0.5 "'3' b. 0.395 "33' c. 0.75 "33' d. 0.711