Question
1 Approved Answer
A project has scope creep. Who has the responsibility to authorize these changes? Group of answer choices The contractors The team members The project management
A project has scope creep. Who has the responsibility to authorize these changes?
Group of answer choices
The contractors
The team members
The project management office manager
The project sponsor