A project has the following activities, times, and precedence relationships: Activity Time weeks Preceding Activities A 3
No answer yet for this question.
Ask a Tutor
Question:
A project has the following activities, times, and precedence relationships:
Activity | Time weeks | Preceding Activities |
A | 3 | NONE |
B | 5 | A |
C | 3 | A |
D | 4 | B |
E | 8 | C |
F | 2 | D, E |
- Draw a precedence diagram for the project.
- Calculate the earliest start and finish times for each of the activities.
- Determine the earliest start, earliest finish, latest start, latest finish, and slack times for each of the activities in the project shown inFigure G.8Posted Date: