Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project has the following characteristics Activity B D E F G H 1 J K L M N Preceding Activity None A B D
A project has the following characteristics Activity B D E F G H 1 J K L M N Preceding Activity None A B D D D B C.E G F,I,J HG M Expected Completion Time (in weeks) 5 2 6 12 10 9 5 9 1, 2 3 9 7 8 5 N- a) Draw a PERT network for this project. b) Find the critical path and the project completion time. c) Prepare an activity schedule showing Es, EF, LS and slack for each activity d) Will the critical path change it activity G takes 10 weeks instead of 5 weeks? If so, what will be the new critical path
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started