A project has the following projected outcomes: $100, $500, and $800. The probabilities of their outcomes are 10%, 50%, and 40% respectively. What is the
A project has the following projected outcomes: $100, $500, and $800. The probabilities of their outcomes are 10%, 50%, and 40% respectively. What is the standard deviation of these outcomes?
Select one:
A. $124
B. $214
C. $546
D. $580