Question

1 Approved Answer

A project has the following projected outcomes in dollars: $250, $350, and $500. The probabilities of their outcomes are 35%, 40%, and 25% respectively. What

A project has the following projected outcomes in dollars: $250, $350, and $500. The probabilities of their outcomes are 35%, 40%, and 25% respectively. What is the standard deviation of these outcomes?

A. $89

B. $178

C. $95.5

D. $363

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Derivatives And Risk Management

Authors: Robert Brooks, Don M Chance

9th Edition

1133190197, 978-1133190196

More Books

Students also viewed these Finance questions

Question

Evaluate the integral. 3t 2 dt t + 1

Answered: 1 week ago