A project has three possible outcomes. The NPV and probabilities for each outcome are shown below: CASE: NPV: Probability BAD -$4,000 0.20 AVERAGE $500 0.50
A project has three possible outcomes. The NPV and probabilities for each outcome are shown below:
CASE: | NPV: | Probability |
BAD | -$4,000 | 0.20 |
AVERAGE | $500 | 0.50 |
GREAT | $10,000 | 0.30 |
What is the expected NPV for this project if our assumptions are correct?
Question 24 options:
$1,050 | |
$2,450 | |
$4,250 | |
$2,167 | |
$600 |