A project indirect costs are $1,000 per day. Currently there are 3 activities available to crash. All can be shortened by up to 1 day
A project indirect costs are $1,000 per day. Currently there are 3 activities available to crash. All can be shortened by up to 1 day and none is on the Critical-Path. Crashing costs are: A for $800 per day. B for $1,200 per day and C for $500 per day. what should you do?A