A project initial cost is I, the present worth of benefit is PWB, the present worth of operation and maintenance cost is PW WAM, and
A project initial cost is I, the present worth of benefit is PWB, the present worth of operation and maintenance cost is PW WAM, and the present worth of salvage value is PWS, which of the following formula is the benefit cost ratio? PWB/(I+PWO&MPWS)PWB/(I+PWO&M+PWS)PWB/(IPWO&MPWS)(PWBPWS)/(IPWO&M)