Question

1 Approved Answer

A project is calculated to have a critical path duration of 10 days with 3 activities on the critical path and corresponding standard deviations A

A project is calculated to have a critical path duration of 10 days with 3 activities on the critical path and corresponding standard deviations A (standard deviation is 2) B (standard deviation is 1) and C (standard deviation is 2). What is the probability the project will take more than 16 days to finish?

Step by Step Solution

3.48 Rating (155 Votes )

There are 3 Steps involved in it

Step: 1

To calculate the probability that the project will take more than 16 days to finish we can use the c... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Algebra

Authors: Margaret Lial, John Hornsby, Terry McGinnis

13th Edition

0134895983, 978-0134895987

More Books

Students also viewed these General Management questions

Question

Customer Name Phone No . Email Revenue Acct ( Credit Limit )

Answered: 1 week ago

Question

Find the vertex of each parabola. f(x) = -3x + 12x 8

Answered: 1 week ago

Question

Write each number in standard notation. 8.761 10 0

Answered: 1 week ago