A project is composed of the following activities. Draw the project network and compute the earliest start, latest start, earliest finish, and latest finish time
A project is composed of the following activities. Draw the project network and compute the earliest start, latest start, earliest finish, and latest finish time for each activity.
Activity | Immediate predecessor | Days |
A | -- | 4 |
B | -- | 9 |
C | A | 3 |
D | B | 8 |
E | B | 7 |
F | D | 2 |
G | E | 5 |