A project is defined by the list of activities in the table shown; use the critical path method to: a. draw the precedence network b.
A project is defined by the list of activities in the table shown; use the critical path method to: a. draw the precedence network b. determine early and late times c. find the critical path d. find the total float and free float of each activity Immediate Activity predecessors Weeks A B D E F G H A A A B CD E,F D GH 1 4 3 7 6 2 7 9 4