Question
1 Approved Answer
A project is expected to cost $185,000 today and earn $394,000 in year 5. There are no other cash flows. Cost of capital is 8.8%.
A project is expected to cost $185,000 today and earn $394,000 in year 5. There are no other cash flows. Cost of capital is 8.8%. What is this project's internal rate of return? Answer in percent, rounded to one decimal place.