Question
1 Approved Answer
A project is expected to cost $85096 up front, and then return $23768 in year 1, $45414 in year 2, and $32710 in year 3.
A project is expected to cost $85096 up front, and then return $23768 in year 1, $45414 in year 2, and $32710 in year 3. If the company demands a 8% return from their projects, what is the net present value of this project? Answers should be to the nearest cent. If your answer is negative please write it as "$-100.03" with the dollar sign before the negative so blackboard can read it correctly.
Step by Step Solution
There are 3 Steps involved in it
Step: 1