A project is faced with a risk that the project team is unable to eliminate. It has
Fantastic news! We've Found the answer you've been seeking!
Question:
A project is faced with a risk that the project team is unable to eliminate. It has a low probability of occurring and will not impact the project, so no additional action is taken. This is known as which one of the following?
A. Transfer
B. Passive acceptance
C. Active acceptance
D. Exploit
Posted Date: