Question

1 Approved Answer

A project is made of the following activities: Task Duration Predecessor(s) ES EF LS LF slack A 2 B 20 A C 5 A D

image text in transcribed
A project is made of the following activities: Task Duration Predecessor(s) ES EF LS LF slack A 2 B 20 A C 5 A D 20 C E 17 B,C.D F 11 D G 2 E.F 1. Complete the table above - ES, EF, LS, LF, Slack (15 points) 2. What is the critical path? What is the project duration? (5 points) 3. Refer to the critical path you found in 2. Assume that every activity is normally distributed. Each activity's mean is given in the table above. Each activity's standard deviation is 20% of its mean (for example, the mean duration of activity A is 2 and its standard deviation is 0.4). What is the probability that the project will last more than 48 days? (10 points)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring Strategy Text And Cases

Authors: Gerry Johnson, Richard Whittington, Patrick RegnÈr, Kevan Scholes, Duncan Angwin

12th Edition

1292282517, 978-1292282510

More Books

Students also viewed these General Management questions

Question

Discuss the role of motivation in financial literacy.

Answered: 1 week ago