A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative. What should the project manager do next?
- A. Review organizational process assets (OPAs) for clarity.
- B. Consult the project charter for next steps.
- C. Confirm the definition of done (DoD) has been met.
- D. Document lessons learned before closing.