Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2

a project is partially complete. the work package estimate was$297000,the contingency reserve is 34.5% and the management reserve is38.5% of the baseline. There are 2 approved change request based on known risks,CR1 which is $7400 and CR2 which is $141000.There is also a 3rd change request pending approval,CR3 which is $131500. What would be the remaining balance left in our contingency reserve if the only funds used from the contingency reserve was 31% of CR

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the remaining balance left in the contingency reserve we need to follow these steps Ste... blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Project Management

Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells

5th Edition

035771573X, 978-0357715734

Students also viewed these General Management questions

Question

= What do you conclude from the above?

Answered: 1 week ago