A project is scheduled to be completed within 1 6 months and the total cost of the project is 2 0 0 , 0 0
A project is scheduled to be completed within months and the total cost of the project is USD. Eight months have passed and USD has been spent. After a closer review, you as a project leader found that only of the work has been completed so far, while work was expected. Complete the following?
Note: Earned Value of completed work times Planned Total Project Cost
Find the following:
PV
EV
SPI
CPI
Find the following:
PV
Find the following:
EV
Find the following:
SPI
Find the following:
CPI
A
B
C
D
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started