Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A Project Manager develops a project management plan and schedule based on an agreed-upon project life cycle of 16 months. Later, due to changing business

A Project Manager develops a project management plan and schedule based on an agreed-upon project life cycle of 16 months. Later, due to changing business requirements, the Project Manager receives a request for completion within 9 months.

How should the Project Manager respond to this proposed change in timeline?

SELECT THE CORRECT ANSWER

A. Work with key stakeholders to identify project requirements that could be reduced

B. Immediately ask project team members to increase the pace of each task within the project

C. Modify the original project schedule so that revised deadlines can be met

D. Meet individually with project team members to discuss how aspects of the project can be completed more quickly than planned

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry

Authors: John R Walker

2nd Edition

013243766X, 9780132437660

More Books

Students also viewed these General Management questions

Question

Peoples understanding of what is being said

Answered: 1 week ago

Question

The quality of the proposed ideas

Answered: 1 week ago