a project manager for a small construction company has a project that was buy for 130000 in a 6 weeks period. according to be schedule
a project manager for a small construction company has a project that was buy for 130000 in a 6 weeks period. according to be schedule the project should have cost 60000 to date. however, it has last 90000 to date. the project is also defined schedule because the original estimates were not accurate who has primary response to solve the problem
project sponsor
manager of project management office
project manager senior management