A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access
A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to water. What should the project manager do next? Start project planning and develop the project management plan. Process a change request for additional funding due to project urgency. Hire local contractors who are familiar with the environment. Face the challenge immediately and start sending relief to the town