A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the

A project manager has developed the following data on a project tasks and duration. Please create an AON diagram, identify the critical path and the expected project duration. The customer has asked for a 95% confidence on the project completion date.Calculate the number of additional weeks the project manager needs to make that commitment.

Time estimation in weeks
Task Predecessor optimistic Most likely Pessimistic
A 3 4 5
B A 1 8 15
C A 2 4 6
D A 4 8 12
E B 7 9 11
F C,B 2 5 8
G E,D 5 7 9
H F,G 4 7 10

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions