A project manager is evaluating a project and initially forecasts that the project will lasts for four years and has its annual marketing and support
A project manager is evaluating a project and initially forecasts that the project will lasts for four years and has its annual marketing and support costs of $1,000,000 and its annual revenue of $10,000,000. The project pays a 40% tax rate on its pre-tax income and its cost of capital is 15%. While analysing a situation that competitors can run their big promotion programs during the projects life, the manager proposes one solution to the situation by increasing the marketing and support costs by 60% of the originally forecasted level and simultaneously lowering the forecasted revenue by 30% of the originally forecasted level. The change in the net present value (NPV) of the project is closest to:
A. -$6,656,717.44
B. $6,166,753.26
C. $6,656,717.44
D. -$6,166,753.26
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started