Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project manager is managing a project. The original scope baseline of the project was budgeted at $200,000. Since work on the project started there
A project manager is managing a project. The original scope baseline of the project was budgeted at $200,000. Since work on the project started there have been twelve authorized and approved changes to the project. The changes have a value of $15,000 and the cost of investigating them prior to their approval was $2,000. What is the current budget for the project?
|
$200,000
|
|
$213,00
|
|
$215,000
|
|
$217,000
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started