A project manager is performing a PERT analysis of her single-path project and determined that the CP expected duration is 59 days with a standard
A project manager is performing a PERT analysis of her single-path project and determined that the CP expected duration is 59 days with a standard deviation of 23.6. Regrettably, the program office, without first consulting the project manager, promised a delivery based on 72 days. Compute the Z-score for the project CP. Express your result as a decimal number rounded to 3 decimal places, if applicable