Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project manager is performing a PERT analysis of her single-path project and determined that the CP expected duration is 56 days with a standard
A project manager is performing a PERT analysis of her single-path project and determined that the CP expected duration is 56 days with a standard deviation of 23.9. Regrettably, the program office, without first consulting the project manager, promised a delivery based on 74 days. Compute the Z-score for the project CP. Express your result as a decimal number rounded to 3 decimal places, if applicable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started