A project manager is using the internal rate of return method to make the final decision on which project (A, B, C, and D) to

A project manager is using the internal rate of return method to make the final decision on which project (A, B, C, and D) to undertake. Select correct answers only.

Year

net flow of A

net flow of B

net flow of C

net flow of D

0

-$108,000

-$88,000

-$63,000

-$65,050

1

$42,000

$25,000

$13,000

$20,000

2

$35,000

$21,000

$17,500

$16,000

3

$30,000

$22,000

$17,000

$16,000

4

$19,000

$24,000

$17,000

$16,000

5

$6,000

$21,000

$17,500

$16,000

Group of answer choices

the lowest IRR calculated for these projects is 9.11%

if your current return is 9.98% will you undertake any of these project? Yes

the highest IRR calculated for these projects is 9.52%

Project C's IRR is 9.11%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

Students also viewed these Finance questions