A project manager of the construction project in the Cal Poly Electronics considers three different time estimates shown below: Index Immediate Predecessors Optimistic (In month)
A project manager of the construction project in the Cal Poly Electronics considers three different time estimates shown below:
Index | Immediate Predecessors | Optimistic (In month) | Most Likely (In month) | Pessimistic (In month) |
A | - | 4 | 7 | 10 |
B | - | 4 | 6 | 14 |
C | - | 6 | 7 | 8 |
D | A, B | 7 | 15 | 17 |
E | B, C | 4 | 5 | 6 |
(a) Calculate the expected time and the variance for each activity. Fill in the blanks. For expected activity time for each activity, carry an integer value. For activity variance, carry two decimal places.
Index | Expected time | Variance |
A | ||
B | ||
C | ||
D | ||
E |
(b) Calculate ES/EF/LS/LF/slack values for each activity. Use Expected activity times that you calculate in part (a) for this question.
Activity | Early Start | Early Finish | Late Start | Late Finish | Slack |
A | |||||
B | |||||
C | |||||
D | |||||
E |
(c) Based on the calculation of estimated times, what is the critical path? Fill in the blanks.
path 1: --> and
path 2: -->
(d) Based on the calculation of estimated times, what is the project variance? Carry two decimal places.
Project Variance =
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started