A project manager states, I know the risk exists, and I'm aware of the possible consequences to my project. I am willing to wait and
A project manager states, "I know the risk exists, and I'm aware of the possible consequences to my project. I am willing to wait and see what happens. I may develop a contingency plan, but I am going to do nothing to affect the probability or impact of the risk." The project manager is exercising which type of risk response? Group of answer choices avoidance transference acceptance mitigation