Question

1 Approved Answer

A project manager wants to assess the risk of scheduling delays. He/she considers that it is very likely to have a delay from 1 to

A project manager wants to assess the risk of scheduling delays. He/she considers that it is very likely to have a delay from 1 to 5 days, which will cost the project less than $10,000. It is likely to have a delay of 6-10 days with an additional cost between $10,000 and $20,000. It is possible to have a delay of 11 to 20 days with a cost of $30,000 to $40,000. It is unlikely to go over this time delay and have a delay of 21 to 30 days, which if it happens will cost $50,000 to $70,000. It is very unlikely that the project can be delayed more than 30 days, which in this case will cost more than $100,000.
(a) Put this information in a Risk Matrix. (b) Show the calculations for the entries of the Risk Matrix. (c) Put the colors on the cells and explain the criteria that you used for the selection of the different colors. (d) Discuss the actions plans that you would put that would correspond to the different colors.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Competitor Analysis In Financial Services

Authors: Ian Youngman

1st Edition

1855733315,1782420053

More Books

Students also viewed these Finance questions

Question

12. What is interoperability? Why is it important?

Answered: 1 week ago