A project manager wants to create a project plan. You tell him that the project plan should include: A. Project management methodology, project management information
A project manager wants to create a project plan. You tell him that the project plan should include: A. Project management methodology, project management information system, and expert judgment B. Deliverables, requested changes and implemented change requests C. Project files and historical information D. List of milestones, Cost and Schedule Baselines, how changes will be monitored and controlled