A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of
A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of the management team was requested on time. Which of the following documents should be reviewed to understand the root cause of this situation? A. RACI B. SOW C. Escalation path D. Communication plan