A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a
A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late finish time of 12. What is the task's slack? OA.9 OB. 5 OC.0 OD.4 OE. 6 O F. 7