A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late
A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late finish time of 12. What is the tasks slack? A. 9 B. 7 C. 0 D. 6 E. 5 F. 4