Question

1 Approved Answer

A project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (pessimistic)

A project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (pessimistic) it will take 15 days, and if conditions are ideal (optimistic), it will take only 3 days. Using the PERT three-point estimation method, what is the expected time for this work package?

18 days

14 days

9 days

26.67 days

None of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

General Management Für Medizinbetriebe

Authors: H.-Jürgen Seelos

1st Edition

3834926906, 978-3834926906

More Books

Students also viewed these General Management questions

Question

social sciencess

Answered: 1 week ago

Question

Describe the environment in which business operates

Answered: 1 week ago